The new depot on Hărmanului Street in Brașov was designed for 157 buses. For vehicles back from their routes to go out again in the morning, the operator must be able to charge them during the hours they are parked. Răzvan Crăciun, Technical Director of RATBV, told the National Public Transport Congress that the power supply project aims to reach, in the end, “somewhere around 10 megawatts.”

RATBV started this project together with Brașov City Hall and the companies involved in building the power supply. The calculation of what is needed covers the buses the operator already has, as well as another 88 electric buses it is expecting. On 19 November in Bucharest, the Technical Director presented the 10 MW figure as the project's target.
157 parking spaces and two connections to the grid
The depot at 49 Hărmanului Street has a slow charging point planned for each of its 157 spaces. The same complex houses the maintenance workshop, the area for periodic technical inspections and the washing station. The city secured European funding for the investment in May 2020. Construction began in November 2023, and work on the depot was completed in December 2025, according to reports in the local press.
The power supply has its own timetable. By summer 2026, RATBV had filed two requests with the environmental authority to connect the depot to two different substations. One is in the commune of Hărman, the other in the Rulmentul area of Brașov, beyond the Timișul Sec stream.
Available power matters for a reason any dispatcher preparing the morning departures knows well. Two buses returning to the depot at the same time can have different charge levels and may be scheduled to leave at different times. How many vehicles can charge at once depends both on the chargers installed and on the power the grid can supply at that moment. The 10 MW Răzvan Crăciun spoke about expresses that supply capacity.
“The road has been hard, because of the permits”
In the discussion in Bucharest, the Technical Director named charging power as one of the first difficulties Brașov met in moving to electric buses. “The road has been hard, because of the permits,” Răzvan Crăciun said. In his view, the operator needs a shorter procedure between the moment it justifies its power requirement and the moment the authorities issue the permits.

Drawing on the supplier's experience, Magda Peșu, CEO of Anadolu Automobil Rom, explained in the same panel why these deadlines matter. The right moment to commission the chargers, both slow and fast, is when the buses arrive. In Brașov, preparing for the 88 vehicles therefore begins with work that passengers cannot see from the bus stop. It determines how many buses will be able to leave fully charged on the first service.
Sources · Răzvan Crăciun at ROPAT · Magda Peșu on connecting chargers · The two planned power connections (in Romanian) · Works timetable and depot facilities (in Romanian)